| Area of new 33/11kV Control Building |
![]() |
| From 275kV Transformer to new 132kV Transformer Bay |
![]() |
| 2 Transformer Bay Extension |
![]() |
| 132kV Switchyard |
![]() |
| 132kV Switchyard |
![]() |
| Inside DC Charger |
![]() |
| 132kV Bus Coupler Control Panel |
![]() |
| 275kV Busbar Protection Panel (High Impedance) |
![]() |
| Areva T&D Kits for SIMS (Substation Interrogation Monitoring System) |
![]() |
| FACIA for 275kV Remote Tap Changer Control Panel |
![]() |
| Indicator at 275kV RTCC Panel |
![]() |
| 275kV Overhead Line Control and Relay Panel |
- Expansion of AIS 132/33kV Transformer Bays include Civil Works (33/11kV Control Building)
- Design Review for 45MVA 132/33kV Power Transformer
- Expansion of Secondary Equipment (CRP, RTCC, BBX, etc)
- Expansion of Telecontrol Equipment (SCS for 132kV, RTU for 33kV)